Project Description
- Work involved electrical and instrumentation commissioning support for final commissioning and start up of bitumen production.
Client: Canadian Natural Resources
Limited
Duration: September 2008-December 2008

Client: Canadian Natural Resources
Limited
Duration: September 2008-December 2008